How are hollow-core slabs transported?
Hollow-core slabs travel flat, stacked on a flatbed trailer, with timber bearers under each slab close to its ends and directly above one another through the stack. The stack is built in reverse erection order, loaded against the headboard where possible, and held down with chains or rated straps over edge protection.
Shimla Transport (Shimla General Materials Transport LLC), Dubai, runs 69 tractor units and 72 A-frame and flatbed trailers from Al Quoz Industrial Area 2 and its Abu Dhabi branch, including 14 flatbed trailers with 12 m decks that carry slabs and other flat-stacked precast.
Why bearer position matters
A hollow-core slab is prestressed to span between its two end bearings. Its strands sit low in the section, so it is strong when supported near the ends and loaded from above, and weak if it is supported somewhere the design did not intend. A bearer at mid-span, or a long unsupported overhang, puts the top of the slab in tension and can crack it before it reaches site.
The manufacturer's handling drawing gives the support points, and that drawing always governs. As an indication of how tight the limits are, one UK hollow-core manufacturer's published method statement places bearers just inside the slab ends, no further in than four times the slab depth, and requires them to sit vertically above one another.
Building the stack
The same rules that apply in the factory yard apply on the trailer.
- Right way up: slabs travel in the orientation they were cast and will be laid.
- Bearers in line: every bearer sits directly above the one below, so the load passes straight down through the timber and not through the concrete between.
- Two support lines: a rigid slab is carried on two bearer positions, so that the trailer can flex under it on the road without lifting the slab off a third support.
- Like with like: similar lengths go in one stack. Shorter or narrower units go on top, never underneath longer ones.
- Sound timber: square-section bearers of even thickness, long enough to carry the full slab width, with no split or rounded pieces.
- Reverse erection order: the slab the crane needs first is the last one loaded.
The load plan
We build the load plan from the slab schedule: marks, lengths, depths and weights. Slab weight per metre rises with depth, so the number of slabs per trailer changes from one job to the next. The plan checks weight against the trailer's payload (25 to 35 t across our fleet) and the route's limits, length against the 12 m deck, and stack height against stability and the clearances on the route. Where slabs of different lengths share a trailer, they go in separate stacks along the deck.
Securing the load
Published load-securing guidance for precast is clear that the weight of concrete does not hold it in place: friction alone cannot be relied on. In practice:
- the stack is loaded against the headboard where possible, or blocked so it cannot slide forward under braking;
- chains or rated webbing straps go over each stack, placed at the bearer lines so the lashings do not slacken as the trailer flexes;
- corner protectors sit wherever a lashing crosses a slab edge, protecting both the concrete and the lashing;
- chains and webbing are never mixed on one load, because they behave differently under tension;
- lashings are checked before departure, after the first stretch of road and again before entering site.
On the road and at site
Heavy vehicle movement in Dubai and Abu Dhabi is subject to permit requirements and restricted hours that vary by road, so each route is timed around the crane slot and the restrictions in force; check the current requirement with the Roads and Transport Authority (RTA) or Abu Dhabi Mobility for each route. Every vehicle in our fleet has GPS tracking and ID-button driver identification, so the site knows where the load is.
At site, the trailer needs firm, level ground within reach of the crane. Lashings come off one stack at a time. Slabs are lifted from the top down with the lifting equipment and lifting points the manufacturer specifies, and the bearers come back with the trailer or stay with the slabs if they are to be stacked on site. Site stacks follow the same rules: level ground that can carry the weight, bearers near the ends and in line.
Frequently asked questions
How many hollow-core slabs fit on one trailer?
It depends on slab depth, length and weight per metre. The limit is whichever comes first: the trailer's payload of 25 to 35 t, the 12 m deck length, or a stack height that stays stable and within the route's height limits. We work it out from your slab schedule.
Where do the bearers go under hollow-core slabs?
Close to the slab ends, at the support points the manufacturer gives, and directly above one another through the whole stack. Hollow-core slabs are not normally supported at mid-span unless the manufacturer's drawing says so.
Can slabs of different lengths travel in one stack?
Similar lengths are stacked together so the bearers stay in line. Shorter or narrower units go on top, never underneath longer ones, and only where the bearers still line up.
What should I send to book hollow-core slab transport?
The slab schedule with marks, lengths, depths and weights; the manufacturer's handling and stacking drawing; collection and delivery addresses; the erection sequence by bay or floor; crane slot times; and any site access limits.
Booking hollow-core slab transport
Shimla Transport moves hollow-core slabs, wall panels, beams and columns, stairs, box culverts and cladding units across all seven Emirates, per trip, by the hour or as a dedicated monthly fleet with drivers. See our precast transport services or send us your slab schedule for a load plan and quote.
Written by the Shimla Transport operations team. Reviewed by Arun Kumar, Shimla Transport. Last updated: 17 November 2026.